July 1, 2002

   

Karen Brown

Program Liaison

CALFED Watershed Program

Department of Water Resources

3374 E. Shields, Room B19

Fresno, CA 93726

  

Dear Karen,

 Please find attached the requisite Monthly Program Report for the Millerton Area Watershed Coalition Program – Contract Number: 4600001799.  The report is for the period of June 1, 2002 through June 30, 2002 – and includes the following:

 

bulletReport Summary – Highlights and Major Accomplishments
bulletReport of Work Completed by Tasks and Subtasks
bulletAttachments of collateral materials developed for the MAWC Program

 Additionally, we have included the Quarterly Reporting information consisting of the following:

 

bulletImportant Upcoming Events
bulletIn-Kind and Cash Match

 At this time, it can be reported that the Millerton Area Watershed Coalition’s activities under CALFED’s Watershed Program are fully in progress.  The two major events in June included a Visioning Workshop and the 1st Steering Committee session.  At least 16 individuals have indicated an interest in serving on the Steering Committee.

Thank you as well for your own participation in the Visioning Workshop.

  

Please let us know if you have any questions or concerns regarding this submittal.

  

Sincerely,

 

_________                __________

Jim Carl

Steve Haze

Program Manager

Program Coordinator


 

The following are the Highlights and Major Accomplishments for this reporting period –

  

Program Planning, Administration and Organization

bulletNotification sent out via USPS mailing and internet distribution to Media, potential Stakeholders and attendees from 1st general session for Visioning Workshop on June 15th and 1st Steering Committee Session conducted on June 27th.
bulletNotice published by Mountain Press

 

bulletConducted Visioning Workshop on June 15th – Noreen McDonald, Facilitator
bulletApproximately 25 attendees
bulletFacilitation of 4 primary questions related to the watershed –
  1. What are the Challenges?
  2. What are the Opportunities?
  3. What should the Coalition do?
  4. What would you like to do?

 

bulletConducted 1st Steering Committee Session on June 27th
bulletApproximately 20 attendees – 16 indicated desire to participate on the committee
bulletOrganizational discussions related to Steering Committee responsibilities

1.      Stakeholder Representation

2.      Selection of Chairperson

3.      Types of Sub-committees

4.      Roles and Responsibilities

5.      Development of a Mission Statement

 

Education and Publicity

bulletWorking at a Watershed Level Conference – 6/3 thru 6/7
bulletWatershed Display at Fire Safe Festival, Auberry – 6/8

Integration and participation with major watershed programs and other CALFED initiatives

bulletCALFED Bay-Delta Program – BDPAC Subcommittee for Watershed Management – 6/21
bulletCALFED Upper San Joaquin River Basin Storage Investigation Stakeholder Group – Review of Technical Memorandum and submittal of comments

 

Outreach, Participation and Collaboration with Resource Centric organizations

bulletUpper Merced River Watershed Council celebration – 6/12
bulletMillerton Lake Visitor / Interpretive Center fire safe landscaping activity, Bureau of Reclamation – 6/19
bulletHighway 168 Fire Safe Council – 6/20
bulletCentral Sierra Watershed Committee – 6/26
bulletCoarsegold Resource Conservation District – 6/27
bulletNorth Fork Mono Rancheria and Sierra  Mono Indian Museum – 6/27

 

Continuation Planning

bulletSubmission of full proposal to CALFED for Upper Finegold Creek Watershed Assessment and Planning under Proposition 13 – 6/5

 

 

The following is the Quarterly Reporting of Additional Information –

 

Upcoming Major Events and Activities

bulletOn-going Steering Committee Sessions (Finalize Stakeholder Representation and other Organizational formalities) – Thursday, July 25, August 22 and September 26.
bullet2nd General Session – August 22nd.
bulletSan Joaquin River Management Program - Action Team Meeting – 7/8
bulletConduct presentation to North Fork Mono Rancheria Tribal Council representatives – (TBD)
bulletUpper San Joaquin River Basin Storage Investigation Stakeholder Meeting – 7/31

 

Major Tasks

bulletFormation of working sub-committees
bulletPlanning for educational workshop
bulletPublish tabulation of Visioning Workshop participant comments San Joaquin
bulletCommence development of Assessment Design

 

Local In-Kind and Cash Match

 

Activity

Amount

Source

Pre-CALFED Planning

$24,032

US Bureau of Reclamation

Pre-CALFED Planning

$1,472

Sierra Foothill Conservancy

Pre-CALFED Planning

$1,000

Program Coordinator

Multi-Media & Computer Equipment

$4,300

Program Coordinator

Mailing to Property Owners

$400

10 volunteers x 2hrs x $20/hr

1st General Session

$3,200

80 attendees x 2hrs x $20/hr

Facilities for 1st General Session

$250

In-kind by Owner

Visioning Workshop

$1,500

25 attendees x 3hrs x $20/hr

1st Steering Committee Mtg

$800

20 attendees x 2hrs x $20/hr

Watershed Conference Scholarship

$300

Calif. State University, Fresno

 

 

 

Total

$37,254

 


   

Collateral Materials

  

bulletVisioning Workshop and 1st Steering Committee Session Notification (Publisher format and Word format)
bulletVisioning Workshop – Presentation Package (PowerPoint format)
bullet1st Steering Committee Session – Presentation Package (PowerPoint format)
bulletSteering Committee Membership List (word Format)
bulletCalendar of Program Coordinator’s Monthly Activities (Excel format)

 

Tabular Summary Report of Contracted Tasks and Subtasks

 

Contract Number: 4600001799

         
 

Contract Approval Date: March 28, 2002

         
 

Contract Start Date: June 15, 2001

         
 

Contract End Date: June 30, 2002

         

Reporting Period: June 1 thru June 30, 2002

PROGRAM TASK DESCRIPTIONS

Planned Complete

Actual Complete

Percent Complete

 

Comments

             

TASK 1: Administration and Organization

 

Task 1a: Identify and appoint Coalition Coordinator

Oct, 2001

Oct, 2001

100%

 

Coordinator, Steve Haze started 10/1 under BOR funds

 

Task 1b: Create a comprehensive mailing list of landowners and other stakeholders in the watershed.

April, 2002

Apr, 2002

100%

 

List of 2500 landowners, 55 Stakeholder, local Government groups and 5 newspapers

 

Task 1c: Contact stakeholders by mail and in person to encourage participation

May,2002

May, 2002

100%

 

Notice to Property owners sent out via USPS on 5/6, Packages sent to Chairs of Fresno & Madera County Board of Supervisors, (55) Stakeholder interests received package via email distribution

 

Task 1d: Prepare and send press releases concerning the formation of the MAWC to media outlets

May, 2002

May, 2002

100%

 

Press Release Packages Sent to (8) reporters representing (5) newspapers - 5/6

 

Task 1e: Convene formative meeting

May, 2002

May, 2002

100%

 

Formative meeting conducted in Friant on 5/23/02 (2.5) hrs. 80 participants w/ approx. 50% property owners in proposed watershed study area

Task 1f: Form Steering Committee, sub-committees

June, 2002

75%

1st Steering Committee session conducted 6/27. Approximately 20 individuals participated & ~16 indicated interest to serve. Subcommittee formation planned for July mtg.

Task 1g: Convene a minimum of 16 Steering Committee meetings

May, 2003

6%

1st Steering Committee scheduled for 6/27/02 (2) hrs. Approximately, 80 individuals are candidates to participate on Steering and subcommittees

 

Task 1h: Convene a minimum of 8 Coalition meetings

June, 2003

 

12.5%

 

1st Coalition meeting scheduled for 5/23/02

             
 

Task Products

         

The products from this task will include: a comprehensive mailing list, press releases, agendas and minutes from 24 meetings, as well as a fully formed Steering Committee and Coalition

Task Products - Comprehensive Mailing list in excess of 2,500 developed. (12) volunteers @ (2) hrs. ea.

             
 

Success Criteria

         

Success will be measured by completion of each project task according to the timetable, the reporting of coalition activities in local newspapers, having a quorum present at all Steering Committee Meetings, having a minimum of 40 stakeholders participate in Coalition meetings and having those participants represent at least six different categories of stakeholders (e.g. rancher, homeowner, federal agency, sportsmen, policy maker, scientist, etc.)

Success Criteria exceeded for 1st meeting - 80 Stakeholders representing 12 categories

             

TASK 2: Training and Outreach

Task 2a: Conduct a total of 4 community education sessions on topics related to watershed protection, restoration, management, and monitoring

June, 2003

25%

Visioning workshop conducted 6/15. Approximately 25 participants.

Task 2b: Make a total of 8 informational mailings to all stakeholders including meeting schedules, agendas, minutes, report summaries, public policy issues and other information of interest regarding watersheds

June, 2003

15%

1st Informational mailing for Stakeholders (property owners sent out USPS). Other stakeholders via email distribution. Informational Package to County Board of Supervisors sent 5/6, Presentation to Fresno Co. Water Advisory Committee conducted 5/16

Task 2c: Share information regarding the activities of the Millerton Area Watershed Coalition with the general public through press releases and community presentations

June, 2003

20%

2nd notification to Press sent out for Visioning & 1st Steering Committee mtg on 6/10. Established display at Fire Safe Festival in Auberry on 6/8

             
 

Task Products

         

The products from this task include: training materials, coalition mailing packets, and press releases.

 

Success Criteria

         

Success will be measured by attendance of at least 40 people at training sessions, their feedback, and completed evaluation forms; more informed participation in coalition meetings; and increased interest in citizen monitoring activities.

             

TASK 3: Assessment

Task 3a: Identification of major stressors and threats to the Millerton Area Watershed with input from a wide range of stakeholders.

June, 2002

June, 2002

100%

Input provided by Visioning workshop participants

Task 3b: Gather and review current and historical data on the watershed processes to establish, as much as possible, a baseline

July, 2002

5%

Listing of historic, current and planned assessments established

 

Task 3c: Evaluate current conditions and use patterns

Sept, 2002

       

Task 3d: Working with partners, collect additional data especially where there are significant gaps in the database.

Jan, 2003

Task 3e: Prepare a written assessment report to be circulated and shared by all interested parties

April, 2003

             
 

Task Products

         

The products from this task will include: lists and inventories of watershed conditions, summaries of research reviewed or tests conducted, and a written assessment report.

             

Success Criteria

The success of this task will be measured by the completion of the assessment report by the target date, the participation in the assessment by stakeholders from at least 8 different stakeholder categories, and the ability to fill in as many data gaps as possible.

Application submitted to CALFED for Finegold upper watershed planning grant for North Fork Community

             

TASK 4: Collaboration

 

Task 4a: Compile a list of potential collaborators among watershed groups and other agencies and organizations

April, 2002

April, 2002

100%

 

Listing of potential collaborators established. Two Pre-program planning sessions held with agency groups

Task 4b: Maintain frequent contact with other watershed groups for the purpose of sharing ideas, strategies and data.

June, 2003

14%

On-going participation with Central Sierra Watershed Committee and Water Advisory Committees for Madera & Fresno Counties. Attendence at Coarsegold and Sierra RCD's. Participation as Stakeholder for Friant Storage Investigation program under USBR/DWR (CALFED)

Task 4c: Maintain frequent contact with local, regional and national organizations with an interest in conservation or watershed protection and restoration.

June, 2003

14%

On-going attendance at monthly CALFED Watershed Advisory Committee meetings - 6/21. Completed Working at a Watershed Level workshop, CSUF - 6/3-6/7

             

Task Products

This will produce ready reference files with technical reports, guides and documents produced by these groups that will assist the MAWC to complete their assessment activities and learn about successful watershed management programs. It will also produce correspondence and other evidence that the MAWC has shared its data and other information with these organizations.

Website established as repository for technical publications and reports. Hyperlinks to key watershed agencies and resources. Resource Documents being collected

             
 

Success Criteria

         

The success of this task will be measured by the number of collaborators involved (10 or more) and the frequency and duration of contact.

Current Collaborators(as of 6/30): Sierra RCD, Coarsegold RCD, Central Sierra Watershed Committee, North Fork Community Development Council, Yosemite-Sequoia RC&D Council, Fresno Co. Water Advisory Committee, Madera Co Water Oversight Committee, Highway 168 Fire Safe Council, California State University - Fresno, Millerton Lake Area Chamber of Commerce

             

TASK 5: Planning

Task 5a: Develop and implement a funding plan for the continuation of the coalition.

May, 2003

According to Staff with State Senate Agriculture and Water Committee (Senator Costa, Fresno), $5 million was included as a budget line item for the watershed program. Indeterminate at this time regarding success as a part of the budget's passage & signature by Governor.

Task 5b: Develop a funding and implementation plan for the creation of a comprehensive watershed management plan.

June, 2003

14%

Upper Finegold Watershed Assessment Proposal under Prop 13 submitted to CALFED - 6/5 based upon collaboration with Watershed and Economic and Resource entitiesin the North Fork geographical area. Engaged in discussions with USBR for additional funds.

             

Task Products

This task will produce commitments from local agencies and organizations for the funds required to continue the operation of the Millerton Area Watershed Coalition. It will also produce at least 3 potential sources for the funds necessary to create a watershed management plan.

Sources for funding include: CALFED, USBR and Prop 40 funding.

Success Criteria

The success of this task will be measured by whether or not the community mobilizes the resources necessary to maintain the coalition. It will also be measured by the number of grantors that show some interest in funding the management plan.

             

TASK 6: Reporting and Presentations

Task 6a: Prepare comprehensive quarterly progress reports on all aspects of project implementation

April, 2003

25%

1st Quarterly Reporting Information submitted 7/02

Task 6b: Prepare a draft final report that summarizes all project activities and accomplishments over the two year period. Send a draft copy to CALFED for comments and observations.

May, 2003

Task 6c: Revise draft final report to include comments from CALFED and submit

June, 2003

Task 6d: Deliver final summary presentation(s) to CALFED as requested.

June, 2003

             

Task Products

This task will produce 8 quarterly reports, a final report, and presentation materials.

             

Success Criteria

The success of this task will be measured by the accuracy, completeness and timeliness of the reports and presentations. All should provide a good reflection of all project activities, accomplishments and problems.

 